Air purifier

Objective Objective

It only takes 30 days from product research and development to product realization, which is a rapid product research and development. Finally, the mass production time is advanced to the 22nd day.

Job Tasks

15

Research and development

20

Mold making

20

Injection molding

15

Foil film development

5

Material inspection

7

Product improvement

Review the Overview

03/2020  

Suzhou & Dongguan, China

In March, it began to enter the mold making process


04/2020

China

We successfully finalised this project on time.


05/2020

China

This batch of 7000 sets has been successfully completed, and all the products have been put into European and American markets


https://www.electrolux.com.cn/

The world's six most influential industrial design awards!

Began to consulting

Please feel free to consult us!