IMR case-Haier Water heaters

Objective Objective

Design and manufacture a complex faceplate for the S3 &P3 . Critical lead time for this project: 40 days. Project done. S3 &P3

Job Tasks

28

Research and development

17

Mold making

10

Injection molding

30

Foil film development

10

Material inspection

5

Product improvement

Review the Overview

 

11/2019

Qingdao&Dongguan, China

In September, it began to enter the mold making process


06/2020

Qingdao&Dongguan, China

We started to work on the Haier Water Heater. This product is a virtual reality device made by Haier.

08/2020

Product launch. We successfully finalised this project on time.