Objective Objective
Design and manufacture a complex 2K Cover. Critical lead time for this project: 40 days T0. 120 days mass production, Project done.
Research and development
Mold making
Injection molding
Foil film development
Material inspection
Product improvement
09/2021
Dongguan, China
Started to work on the frame cover.
10/2021
Dongguan, China
Mold Finished, T0 trial and test manufacture.
01/2022
Finished all tesing, start mass production.