IMR case-HSALUS Quantenthermostat

Objective Objective

Design and manufacture a SALUS CONTROL panel. Critical lead time for this project: 60 days T0. 90 days mass production, Project done.

Job Tasks

14

Research and development

40

Mold making

20

Injection molding

60

Foil film development

15

Material inspection

60

Product improvement

Review the Overview

 

09/2020

Dongguan China

Started to work on the SALUS controls



10/2020

Dongguan, China

Mold Finished, T0 trial and test manufacture.


12/2020

Finished all tesing, start mass production


Website: salus-controls.com


The world's six most influential industrial design awards!

Began to consulting

Please feel free to consult us!