IMR case-Dreame H10 vacuum cleaner

Objective Objective

From product research and development to mass production time is tight, it will be put on the market within 3 months

Job Tasks

14

Research and development

40

Mold making

20

Injection molding

60

Foil film development

15

Material inspection

60

Product improvement

Review the Overview

 

07/2020

Dongguan, China

In June 2020, it began to enter the mold making process


02/2021

Dongguan, China

We successfully finalised this project on time.

04/2022

In April, it entered mass production and was successfully put on the market.