Air cleaning machine panel
Objective Objective
From product research and development to mass production time is tight, it will be put on the market within 3 months
Job Tasks
20
Research and development
18
Mold making
20
Injection molding
20
Foil film development
10
Material inspection
12
Product improvement
Review the Overview
07/2023
Dongguan, China
In July 2024, it began to enter the mold making process
09/2023
Dongguan, China
We successfully finalised this project on time.
10/2023
In June, it entered mass production and was successfully put on the market.