Air cleaning machine panel
Objective
From product research and development to mass production time is tight, it will be put on the market within 3 months
Job Tasks
20
Research and Development
18
Mold Manufacturing
20
Injection Molding
20
Foil Film Research and Development
10
Material Inspection
12
Product Improvement
Review the Overview
07/2023
Dongguan, China
In July 2024, it began to enter the mold making process
09/2023
Dongguan, China
We successfully finalised this project on time.
10/2023
In June, it entered mass production and was successfully put on the market.
The world's six most influential industrial design awards!
The brands above are listed in no particular order
Began to consulting