Objective
Design and manufacture a complex 2K Cover. Critical lead time for this project: 40 days T0. 120 days mass production, Project done.
Research and Development
Mold Manufacturing
Injection Molding
Foil Film Research and Development
Material Inspection
Product Improvement
02/2024
Dongguan, China
In February 2024, it began to enter the mold making process
05/2024
Dongguan, China
We successfully finalised this project on time.
06/2024
In June, it entered mass production and was successfully put on the market.
The panel and buttons are made with IMR technology, This advanced technique achieves a high-quality silver-plated finish and hollowed-out text effect simultaneously during molding. This integrated manufacturing solution significantly reduces production costs for our clients.
Award Information
The world's six most influential industrial design awards!



























Please feel free to consult us!