Objective
Design and manufacture a complex 2K Cover. Critical lead time for this project: 40 days T0. 120 days mass production, Project done.
Research and Development
Mold Manufacturing
Injection Molding
Foil Film Research and Development
Material Inspection
Product Improvement
02/2024
Dongguan, China
In February 2024, it began to enter the mold making process
05/2024
Dongguan, China
We successfully finalised this project on time.
06/2024
In June, it entered mass production and was successfully put on the market.
The panel and buttons are made with IMR technology, This advanced technique achieves a high-quality silver-plated finish and hollowed-out text effect simultaneously during molding. This integrated manufacturing solution significantly reduces production costs for our clients.